Water supply and drainage

Tab Water and heating, buttons Water supply and Drainage. Here you place outlets for plumbing fixtures, run cold and hot water and drainage pipes, check them by calculation according to SP 30, and compile the album. Above the Water supply and Drainage tiles there is a list of steps Auto layout · Floor N: 1 Outlets, 2 Pipes with a choice of layout, 3 Calculation and checks. A completed step has a green check mark and Redo, the current one is highlighted and carries the main button, and the following ones are marked with a number in a circle.

Tasks in this topic

  1. How to place outlets for fixtures and appliances

    WhereWater and heating tab → Water supply or Drainage → step 1 Outlets above the tiles, Place button (when all fixtures have outlets, Redo).

  2. How to place an outlet, manifold or valve manually

    WhereWater supply → Water outlets, Manifold and valves; Drainage → Drain outlets, Cleanouts and valves.

  3. How to run a pipe

    WhereWater supply → Water risers and pipes (cold В1, hot Т3, circulation Т4) or Drainage → Sewer riser and pipes (К1).

  4. How to build pipes automatically

    Wherestep 2 Pipes above the Water supply and Drainage tiles, the Build button; in the Calculation and checks window, the Build pipes button above the remarks.

  5. How to check with a calculation

    Wherestep 3 Calculation and checks, above the tiles Water supply and Drainage (the number of issues is next to them); the window Water and drainage · calculation per SP 30 opens. On the left are the input data, on the right the totals as tiles, issues, flows by floor, head, stacks, pipes and the specification.

  6. How to assemble the VK set: water and drainage

    WhereDrawings → Export → VK set: water and drainage or the Album button in the Calculation and checks window. Heating and ventilation go in a separate HVAC set (Heating, underfloor heating, air conditioning, ventilation): per GOST R 21.101-2026, cl. 4.2.4, each main set has its own designation with a mark and its own numbering, and the standard does not allow combining VK and OV. The stamp reads project-VK.