How to place an outlet, manifold or valve manually

WhereWater supplyWater outletsManifold and valvesDrainageDrain outletsCleanouts and valves

Steps

  1. Select a tile: cold or hot water outlet, drain outlet, floor drain, manifold, ball valve, filter, meter, check valve, pressure reducer, motorized valve, cleanout, vacuum valve or drain outlet.
  2. Click on the plan near a wall, and the item will stick to the wall with its back. A floor drain and a drain outlet are placed on the floor.

What to know

  • A manifold combines a pair of headers, cold and hot, into one item.
  • A meter is installed at a height of 50–150 cm from the floor (SP 30, cl. 12.5), otherwise the calculation will give a remark. In its window there is Meter size (DN15–DN32, DN15 by default): pressure loss depends on it.
  • The window of a drain outlet and a floor drain has Branch diameter. If it is not set, the appliance's branch is used.